Scope management process
Project scope management includes ensuring that the project does and does only all the work required to successfully complete the project processes. It defines the project boundaries and identifies what is within and what is outside the project.
Planning scope management
Creates a scoping management plan that describes how project scope is defined, identified and controlled. The plan provides guidance on how to manage project scope and is part of the project management plan.
- Development of a scope management plan
- Definition of scope management approach
- Identification of demand management processes
Collection of needs
Needs form the basis for the scope of the project.
- Identify and record the needs of the people involved
- Needs tracking matrix
- Needs prioritisation
Definition Scope
The process of developing a detailed description of the project and product. The main output of the definition is the project scope statement.
- Development of detailed project scope instructions
- Identification of project boundaries
- Define acceptance and inspection criteria
Create WBS
The process of decomposing project deliverables and project work into smaller, more manageable components.
- Dismantling project work
- Define Work Pack
- Create WBS Dictionary
Confirmed range
The process of formal acceptance and inspection of deliverables of completed projects makes the acceptance and inspection process objective and enhances the likelihood of receiving and inspection of final products, services or results.
- Inspection of deliverables
- Obtain formal acceptance by client/initiator
- Processing of receiving and inspection issues
Scope of control
Oversee the scope status of projects and products and manage the scoping baseline change process. Ensure that all change requests, recommended corrective measures or preventive measures are addressed through the change control process.
- Monitor range status
- Changes in the scope of management
- Preventing the spread of the epidemic
Scope management tools and technologies
Effective scope management requires the application of a variety of tools and techniques to clarify project boundaries, define needs and control changes in scope.
Work decomposition structure (WBS)
The breakdown of project deliverables into smaller and easier-to-manage components is the underlying framework for the scope of the project.
Needs tracking matrix
Linking demand from source to a table of deliverables to meet demand to ensure that demand is not left out.
Scope model
Visualizes the scope of the project in the form of charts, flow charts, etc., including context charts, case charts, etc.
Decision-making techniques
For needs prioritization and scope decision-making, including voting, multi-standard decision-making analysis, etc.
Scope statement
Detailed description of project scope, key deliverables, assumptions and constraints.
Change control system
Formal process to manage submission, assessment and approval of project scope change requests.
Demand collection techniques
| Technology | Description | Applied scene |
|---|---|---|
| Interviews | Direct communication with the ministry and access to information | Key people, complex needs. |
| Focus group | Interactive panel discussion led by the moderator | Exploring specific themes and collecting group feedback |
| Questionnaire | Circulation of written questions to a large number of respondents | Geographically dispersed groups, statistical needs |
| Observation | Direct observation of user operations in the working environment | User tasks, workflow analysis |
| Prototype method | Create an expected product model for feedback | User interface, innovation products |
Common issues and challenges in scope management
Scope spreads
The gradual increase in the scope of the project without control is the most common issue of scope management.
- Reason: Lack of defined scope, lack of change control
- Impact: cost overruns, delays in progress
- Solutions: change control system established, project boundaries clarified
Fuzzy demand
The lack of clarity in the definition of needs leads to later work returns and disputes.
- Reason: Inadequate collection of needs and insufficient involvement of practitioners
- Impact: Quality deficiencies, client dissatisfaction
- Solutions: use multiple needs collection techniques and establish a needs tracking matrix
It's a human conflict.
Different actors have different expectations and requirements with regard to the scope of the project.
- Reason: No identification of all the actors, priority of need conflicts
- Impact: project delays, low team morale
- Solutions: stem people analysis, decision-making processes established
Range plating gold
The project team adds additional functions that are not required beyond the range.
- Reason: Overinvolvement of developers and misapprehension of needs
- Impact: Waste of resources and possible introduction of new deficiencies
- Solutions: strict adherence to scope benchmarks, enhanced team training
Best practices in scope management
Clear definition of scope
Develop detailed project scope instructions, including:
- Product scope description
- List of deliverables
- Acceptance and inspection standards
- Exception of project liability
- Constraints and assumptions
I'm involved.
Ensure full participation of key stakeholders in the management of:
- Full participation in the needs-gathering phase
- Consensus at the definition stage of scope
- Formal acceptance and acceptance during scope confirmation phase
- Participation in decision-making in change control processes
Change control process
Establishment of an effective change control system
- All changes must be submitted in writing
- Assessing the impact of changes on scope, progress and costs
- Approved by the Change Control Board (CCB)
- Update scope benchmarks and related documents in a timely manner
Continuous Scope Validation
Validation over the life cycle of the project:
- Regular inspection of deliverables
- Comparison with scope benchmarks
- Identify deviations in a timely manner
- Take corrective measures
Key factors for successful scope management
- Clear definition of scope - Make sure all the people involved have a common understanding of the scope.
- Effective communication - Keep the message between the team and the team.
- Strict change control - Prevention of unauthorized changes
- Detailed WBS - Provide complete breakdown of project work
- Ongoing surveillance - Regular comparison of actual performance and scope benchmarks
Example of work breakdown structure (WBS)
The work breakdown structure (WBS) is the hierarchy of the full range of work that the project team needs to implement to achieve the project objectives and create the deliverables required. The WBS organization also defines the overall scope of the project.
WBS Creating Guide
| Principles | Description |
|---|---|
| 100% rule | WBS must include 100% of project work, including internal, external and temporary work |
| Results orientation | WBS should focus on deliverables rather than activities |
| Appropriate level | Disaggregated to manageable work packages, usually within 80 hours |
| We're independent. | The overlap between work packages should be minimized |
| Quantitative | Each work package should have clear criteria for acceptance and inspection |