Comprehensive analysis of earned-value management methods and indicators in project management
Earned Value Management, EVM is an integrated approach to measuring project performance objectively, in terms of scope, progress and resources. It compares the planned workload, actual earnings and actual costs to determine cost and progress performance.
EVM provided early warning of the project ' s state of health by comparing completed work with planned work and helped project managers to take corrective measures in a timely manner.
Definitions:The value of the plan is the approved budget allocated to an activity, also known as the budget for the planned work (BCWS).
Formula:PV = percentage of planned completion x BAC
Definitions:The actual costs are the total costs incurred as a result of the completion of the work during the given time period, also referred to as the actual costs of the completed work (ACWP).
Formula:AC = actual cost spent
Definitions:The earned value is the approved budget for completed work, also known as the cost of the completed work budget (BCWP).
Formula:EV = percentage actually completed x BAC
Definitions:Progress deviations are an indicator of project progress performance, indicating the difference between the earned value and the planned value.
Formula:SV = EV - PV
Interpretation:SV > 0 indicates advance, SV < 0 indicates delay
Definitions:Cost deviations are an indicator of the project ' s cost performance, indicating the difference between the earned value and the actual cost.
Formula:CV = EV - AC
Interpretation:CV > 0 for cost savings, CV < 0 for cost overruns
Definitions:The Progress Performance Index is an indicator of the efficiency of project progress and represents the ratio of earned value to planned value.
Formula:SPI = EV / PV
Interpretation:SPI > 1 indicates progress is advanced, SPI < 1 indicates progress is lagging behind
Definitions:The cost performance index is an indicator of the cost-effectiveness of the project, which is expressed as a ratio of the earned value to the actual cost.
Formula:CPI = EV / AC
Interpretation:CPI > 1 for cost savings and CPI < 1 for cost overruns
Definitions:The completion budget is the sum of all budgets established for the work to be carried out.
Formula:BAC = plan value
Definitions:The estimated cost of completing all the remaining projects is yet to be estimated.
Formula:ETC = (BAC - EV) / CPI (typical deviation)
or ETC = BAC-EV (Atypical deviation)
Definitions:Performance indicators are still required for completion in order to achieve specific management objectives and the cost-efficiency indicators that must be met for the remaining work.
Formula:TCPI = (BAC - EV) / (BAC - AC)
Enter the following values, and the system will automatically calculate all earned value management indicators: